The Foundry

See most recent update here.

Concept Submissions - Coming to Downtown 2018

The Foundry (formerly called The South Catalyst Project) is a redevelopment in Downtown Loveland.  The project is mapped from the blocks between Lincoln and Cleveland Avenues from 3rd Street. south to 1st Street.

The South Catalyst name originated in 2009 during a study of Downtown Loveland. Demolition of the project began in February 2016. During Spring 2016, 15 existing buildings were razed, creating a blank canvas for the development team to begin the phased execution of the Foundry plan. To learn more about the evolution of the Foundry, visit the City of Loveland.

Project Facts         Project Timeline
Total Land Area 3.9 Acres  Public Parking Garage    June 2018
Total Residential Units 155  Lincoln Mixed  August 2018
Total Commercial / Retail 14,206 SF  Cleveland Mixed  October 2018
Hotel 7 Screens / 625 Seats  Public Plaza  October 2018
Public Plaza 35,000 SF  Theater  November 2018
Public Parking 460 Stalls  Hotel  February 2019

 

 

The Foundry - UPDATE July 23, 2017 to July 29, 2017

What will you see?

  • Caisson construction for the garage was completed.
  • Lincoln Avenue Building first floor columns are complete except remaining entry column on northeast corner.
  • Garage wall formwork began.
  • Garage stairwell and elevator mat slabs were formed; reinforcing placed.
  • Construction dewatering continues with regular sampling.

Caisson Installation at Southeast Corner of Garage

Lincoln Building North Entry Columns

Garage Foundation Wall Construction

Garage Elevator and Stairwell Construction

Caisson Installation along Cleveland for Garage

Lincoln Building First Floor Column Construction

 

The Foundry - UPDATE August 15th through September 2nd, 2016

Weeks 12-14

What will you see?

  • The two car garage that is currently sitting on 2nd Ave will be transported off site by Powell Moving on August 14th around 2:00 AM (Traffic Notice).
  • The four car garage that is currently sitting on 2nd Ave will be transported off site by Powell Moving on August 21st around 2:00 AM (Traffic Notice).
  • The Contractor will be repairing the sidewalk on the North border of 216 E. 3rd Street (old tire center) along with minor repairs to East 3rd St.  This sidewalk will be closed from August 22 to August 26.  Traffic control measures will be in place during the street repair.   The 5 parking stalls on the North border of the 216 E 3rd property will be roped off until the work is completed.  (Traffic Notice).
  • 216 E. 3rd Street lot will be converted back into a temporary parking lot.
  • All the land in-between Opera Alley and 1st Street will be seeded for erosion control
  • Final site fencing shall be installed around the first week of September.
     
    The ‘NON-EMERGENCY” contact number for the project is:  720-505-8776. There is a recording that is answered “Stephen P. Di Nardo Consulting Project Information Line – please leave a detailed message and someone will get back to you within 24 hours.

The Foundry - Update July 25, 2016

Week 10

What will you see?

  • The demolition of the old tire center located at 216 E 3rd Street
  • The demobilization of the job trailer located at 216 E 3rd Street.  The DiNardo Management Group and Hudspeth will move into 320 N Cleveland Avenue for the remainder of the project.  The job trailer will be removed sometime between July 18th and July 29th.
  • The Environmental Abatement phase of the project is now complete.
  • There are no anticipated traffic control measures.

The NON-EMERGENCY contact number is 720-505-8776.  This is a recording that is answered “Stephen P. DiNardo Consulting Project Information Line”.   Please leave a message and we will get back to you within 24 hours.  This is a project contact line. 

On site, Economic Development Manager Mike Scholl and
Demolition/Abatement Project Manager Stephen DiNardo. July 6, 2016

 


The Foundry - UPDATE  July 18, 2016

Week 9 – July 18-22 

Traffic Notice: 

Project crews will be working in Lincoln Avenue again on the 20th to complete the sewer disconnection.  

The NON-EMERGENCY” contact number is 720-505-8776.  There is a recording that will be answered “Stephen P. Di Nardo Consulting Project Information Line”.  Please leave a message and they will get back to you within 24 hours.


The Foundry - update May 31, 2016

DEMO UPDATE! What’s happening? Week 3 and 4 - May 30th thru June 10th

What the public will see:

  • The Contractor will be mobilizing 1 or 2 excavators and begin work on the sanitary sewer line decommission.
  • The Contractor will continue the environmental remediation of all properties.
  • The Contractor will begin removing all the tree stumps.

There are no anticipated traffic control measures.
 
NON-EMERGENCY Contact Number: 720-505-8776
This is a recording that is answered, “Stephen P. Di Nardo Consulting Project Information Line. Please leave a message and we will get back to you within 24 hours.


The Foundry - Update May 18, 2016

The KUSA-9News story on the South Catalyst project that ran three times last night. 

Reporter Dan Grossman was here in Loveland, in the wettest of circumstances, to cover the beginning of demolition/remediation as we described in a media release last week. Instead, he was mostly indoors (thanks to the rain!) with Mike Scholl at the Civic Center and Clay Caldwell at Mo Betta Gumbo.

Rain delays $60 million Loveland construction project


The Foundry - UPDATE May 11, 2016

Click here to see demolition map. Click here to download demolition map (11 MB .PDF)
Click here to see conceptual renderings under consideration.

The South Catalyst Project is underway!

The City has issued the official “Notice to Proceed” to Hudspeth and Associates, effective May 16th. 

Following are the activities that will occur in the next two weeks:

What will you see?

  • The contractor will be installing the perimeter fence around the construction site. 
    Please take special note of these closures and possible detours (see drawing below):
    • 2nd Avenue from Lincoln to Cleveland will be gated and closed for the duration of the project. 
    • Opera Alley from Lincoln to Cleveland will be gated and closed for the duration of the project. 
    • The perimeter fence will be set back in the 270 E 3rd Street parking lot to encompass the 12 stalls to the West and 7 additional stalls to the Southwest.  Upon completion of the demolition and asphalt repaving of the 216 E 3rd Street property, the fencing will be removed and the parking spaces will be available again.
  • The contractor will be mobilizing their job trailer to be located at 216 E 3rd Street.
  • The contractor will be mobilizing some heavy equipment.  All equipment will be kept inside their perimeter fence.
  • The contractor will be marking utility locates.
  • Consultants mobilized will include SPD Consulting (Project Manager), Pinyon Environmental, Colorado Civil Group, and SJR Environmental. 

What activities will begin?

  • The Contractor will commence the environmental remediation of all properties
  • The Contractor will start demolition of structures where no environmental abatement is required.
  • The contractor will be installing the Storm Water Management and Erosion control measures.

Special Note:
Please contact Stephen DiNardo at 720-505-8776 (NON-EMERGENCY)

This number takes you to a recording that is answered,  “Stephen P. Di Nardo Consulting Project Information Line.”  Please leave a message and you will receive a call back within 24 hours.  This same number will also be posted on project banners and noted on the project trailer.

Downtown Loveland Colorado, South Catalyst Project Map

South Catalyst Proejct - Conceptual Renderings

 

350 N Cleveland Ave Loveland, Colorado 80537   |   970.541.4333

Office Hours: Monday - Friday, 9:00 AM - 5:00 PM